把测量课程的作业题发上来,在学校系统里面可以无限次做,按最高分给。我最后做完了满分。在这分析第二次做的题目,有几道错题。提醒自己。需要正确答案的话,感兴趣可以自己检索。
Score for this attempt: 260 out of 290
Submitted 14 Jul at 23:57
This attempt took 42 minutes.
Question 1
10 / 10 pts
What is the nominated size of the lintel for brickwork if the opening is 1808mm?
110x90x8 UA 150 EB
150x90x10 UA 150 EB
150x90x8 UA 150 EB
150x70x8 UA 150 EB
The lintel is not nominated
90x70x8 UA 150 EB
Question 2
10 / 10 pts
How many light points are in this project internally and externally? (Not counting 100 recessed lights)
Enter a number only, for example, 16
Question 3
10 / 10 pts
What height is given on the temporary bench mark and where is it?
A temporary benchmark is a reference point to determine heights and levels for the project.
(Think about what would be the abbreviation of 'Temporary Bench Mark')
10.33 top of driveway
10.82 back corner of property
10.20 top of kerb
10.928 top of garage floor
11.10 floor level of building
10.00 top of electrical pit
Question 4
10 / 10 pts
What is the bearing of the front boundary of this project?
255 13" 0"
10 42" 20"
268 18" 0"
288 18" 0"
16 42" 20"
100 42" 20"
Question 5
10 / 10 pts
How many down pipes are on this project? Enter a number as your answer, for example, 22
Question 6
10 / 10 pts
What is the difference in height from the FFL of the inside of the dwelling to the FFL of the Garage?
Enter a number for example 263
Question 7
10 / 10 pts
What is the % of the total site coverage?
Enter a number only, for example 29.63
Do NOT enter the percentage symbol.
IncorrectQuestion 8
0 / 10 pts
Where are the finials situated on this project?
On the floor plan
Each side of the garage door
On the roof plan
Over the bay window
On the site plan
Each gable apex
Refer elevations
Question 9
10 / 10 pts
What is the Lot number of the project site?
Enter a number for example 654
Question 10
10 / 10 pts
What is the nominated pitch of the roof?
Enter a number only, for example, 45
Question 11
10 / 10 pts
Are the rafters to be located over studs?
True
False
Question 12
10 / 10 pts
What scale is the Site Plan?
1:250
1:500
1:100
1:200
1:1
1:50
Question 13
10 / 10 pts
What is the height of the FFL on this project?
10.20
11.10
10.928
10.00
10.33
10.82
Question 14
10 / 10 pts
What is the set out dimension to the corner of the garage?
Enter your answers in mm, for example 6479
Do NOT include the 'mm' in your answer.
Do NOT use commas (,)
Enter only the number.
Question 15
10 / 10 pts
What is the nominated capacity (in litres) of the rain water tank?
Do not use commas or the 'litre' symbol; enter only the numbers, for example, 3000
1500
2000
500
1000
Question 16
10 / 10 pts
All concrete works should comply with what Australian standard?
Enter your answer as 1234
Do NOT enter AS, or the decimal point and version number; for example 4550
Question 17
10 / 10 pts
What is the size and type of piping nominated for the storm water drains?
70mm UPVC Stormwater pipe
110mm UPVC Stormwater pipe
150mm UPVC Stormwater pipe
90mm UPVC Stormwater pipe
Question 18
10 / 10 pts
What does the abbreviation (AJ) stand for and how many are to be installed in this project?
Enter one word in each box and for how many enter a number for example 25
Use lower case, NOT UPPER CASE
Answer 1:
articulation
Answer 2:
joint
Answer 3:
16
Question 19
10 / 10 pts
Termite protection is required on this project, which Australian standard should it be in accordance with?
Enter your answer as 1234
Do NOT enter AS, or the decimal point and version number.
Question 20
10 / 10 pts
What is the member size of the ceiling joists for this project?
90x35
120x45
150x38
100x38
100x50
90x45
IncorrectQuestion 21
0 / 10 pts
What is the overall size of Bedroom 1, not including the Ensuite and WIR, which are separate areas?
Your answer should be in square metres for example 14.63
Do NOT use the symbol m2.
12.96
Bedroom 1 size is 3600 x 3600 or 3.6 x 3.6
Question 22
10 / 10 pts
Bedroom 3, Laundry and Bathroom face approximately which direction?
East
West
North
South
Question 23
10 / 10 pts
Where is the main sewer pit located relative to the Building?
Northeast corner
Northwest corner
Southwest corner
Southeast corner
Question 24
10 / 10 pts
Where is the 11.0m contour line located relative to the Building?
Southeast corner
Northeast corner
Northwest corner
Southwest corner
Question 25
10 / 10 pts
Referring to Section A-A, on the ‘Section and Details’ drawing, what is the type of roof construction?
Truss Roof
Skillion Roof
‘Conventional’ Pitched Roof
Domed Roof
Question 26
10 / 10 pts
What kind of hinge is nominated to be installed on the sanitary compartment (WC, toilet) doors?
Butt hinge
T hinge
Fixed pin hinge
Self closing hinge
Loose pin hinge
Lift off hinge
Question 27
10 / 10 pts
The price for one pair of lift-off hinges is $7.00
Assuming 1 Pair of lift-off hinges per Sanitary Compartment (WC) door, what is the cost for lift-off hinges for this job?
IncorrectQuestion 28
0 / 10 pts
Determine the difference in height of the FFL of the main residence above or below the TBM (top of elec. pit).
The FFL of the main residence is [1.1]m the TBM (top of elec. pit).
Enter dimensions in metres, for example: 1.3 (Use only 1 decimal place and Do NOT enter the metre symbol, 'm')
If it is higher, enter: above
If it is lower, enter: below
Answer 1:
below
Question 29
10 / 10 pts
According to the Site Plan, the difference in height between the Northeast and Southwest corners is 1100mm (11.16 - 10.06)
Given that the FFL is over 1000mm higher than the existing (pre-construction) ground level at the front of the block this would likely mean that:
Construction will need to be on stumps
Trees will need to be removed
All the fences will need to be replaced
The land will be cut towards the rear (North) and filled at the front (South).
Quiz score: 260 out of 290
PreviousNext
Last attempt details:
Time: 42 minutes
Current score: 260 out of 290
Kept score: 260 out of 290