帮忙看看这2个报价合理么,感谢。 都是白人的。
卫生间大概地面面积4个多平方。 基本就是原地方换shower screen, 马桶,vanity,然后瓷砖上墙, 还有就是窗户要改造一下。
quote 1 没有包括卫生间天花板重做
QUOTE 1:
Disconnect plumbing & electrical services, sanitary ware, vanity & tapware
2. Remove shower cubicle.
3. Remove existing window and prepare opening for smaller replacement
approx 600 h x 450 w
4. Re brick up the internal and external leaf on the left hand side of window opening
where the proposed shower alcove is
5. Supply and install replacement aluminium window approx 600 h x 400 w
6. Remove all wall tiles and make good render in prep for retiling
7. Re work hot & cold water supply and vanity unit drainage to revised layout
8. Remove entire tiled floor & screed.
9. Tiling, re screed floor to correct levels, waterproof floor and walls all in accordance
with AS standards.
10. Re tile floor and walls to ceiling, grout, silicon seal junctions.
11. Supply and install vanity, tap ware, rails, toilet as per below specifications.
12. Supply and install shower screen as per below specifications.
13. Apply sealer coat to ceiling, apply paint finish in ceiling white x 2 coats
14. Reconnect electrical power and switches.
15. Clean up associated debris on completion.
16. Supply labour and materials.
PC Sums $ 3,500.00
Wall & floor tiles builders range @ $30 m2
Vanity basin
Toilet suite
Tapware
Shower cubicle
Definition of PC Sum & Provisional Sum
A PC item is an amount of money included in a contract sum to purchase a specified item
such as tiles, taps, doors or bathroom fittings. ... A provisional sum is an amount of money
included in the contract sum to cover work or materials, or both, the extent of which cannot
be specifically detailed when entering a contract.
Alterations will incur 15% builders margin.
General Notes
1. No allowance made for handling asbestos
2. No allowance made for unforeseen items
3. Owner to clear contents as required prior to works proceeding
4. Works to carried out during normal working hours 7.30am - 5.00pm
5. Amenities, power & water to be made available.
6. No allowance to alter drain locations.
7. No allowance for replacement of concrete floors.
8. Allow for supply and install standard 55mm cornices to ceiling.
9. Allow for all rubbish removal.
10. No allowance for major wall repairs
Sub-Total ex GST $18738.00
GST $1873.80
Total inc GST $20611.80
QUOTE 2:
Description Amount AUD
To demo bathroom removing all fittings, fixtures and so forth
To supply skip bin for duration of project for building waste only
To cut in new window to external wall and fit new steel lintel
To supply and install new window
To brick up internal of old window and external as required in similar style bricks
To alter plumbing to suit new fixtures
To render walls through out
To screed floors through out
To waterproof throughout to meet regulations
To tile floor in large format tile
To tile walls floor to ceiling in standard lay large format tiles
To grout and silicone
To replace ceiling with new gyprock ceiling
To replace cornice
To second fix plumbing as required
No allowance for shower screen
No allowance for electrical
No allowance for sanitaryware tapware or tiles
No allowance for works not listed above
No allowance for asbestos or associated works
21,100.00
Subtotal 21,100.00
TOTAL GST 10% 2,110.00
TOTAL AUD 23,210.00
|
|