prestart meeting是讨论什么的? 从动工开始, 到handover一般要6-7月.. builder包driveway, fence和landsc ...
after the prestart meeting, they will submit those plans to council. and any changes after prestart meeting, they would charge you for amendement.
I'm based in Perth. they advised construction work will cost 5 months, and paper work is about 5-6 months. so, luckily in 10 months would complete the work. however, there are too manythings are out of our controls. just could hope the best, and prepared for the wrose from time wise.
it's all depend on your contract, it's my first time build. and I didnt know I could negotiate and bargain hard with them. so, I didnt bargain at all.
fence and front landscape is free of charges, it's included with my land purchase. I think drive way is included into my contract.
the crossover charges, you would need to pay half of the cost, and council would pay the other half.
does your building contract includes soakwells as well? |