再贴一份作业
2.2 Estimating Assessment Task 2 - General Knowledge Quiz
Instructions
Refer to the Estimating Assignment 2 - Task 1 Student Guide, if required, and answer the following questions.
Take the quiz again
* Some questions not yet graded
Correct answers are hidden.
Score for this attempt: 12 out of 20 *
Submitted 22 Jul at 12:28
This attempt took 41 minutes.
Question 1
1 / 1 pts
Refer to the NCC 2019 Vol. 2, Section 3, Part 3.9.1, Clause 3.9.1.3
What is the maximum gradient of an external ramp serving an external doorway or a ramp within a building?
1:8
1:10
1:12
1:6
Question 2
1 / 1 pts
Refer to the NCC 2019 Vol 3, Section D, Part D1 Excessive Noise, Clause DP1.2
What must Plumbing and drainage systems be designed to reduce?
the transmission of airborne and/or impact generated sound
the water pressure in a basement
the flow of stormwater through a 100mm pipe
the transmission of odours
Question 3
1 / 1 pts
Standards Australia is the organisation that develops various Australian Standards.
SAI Global is the publisher that has an exclusive licence over the distribution and sale of Australian Standards.
Which of the following options would NOT be considered suitable?
A copy offered on Gumtree
Purchase via the official SAI Global website
Purchase via the official Standards Australia website
Through Swinburne Library’s student access to SAI Global
Question 4
1 / 1 pts
You are planning your upcoming project, which involves demolition of an existing dwelling, including some associated excavation works.
It is critically important to comply with the relevant codes of practice, standards and legislative requirements.
Compliance with which of the 4 following codes, standards or legislation would be most important?
Safe Work Australia Demolition Work Model Code of Practice
WorkSafe Vic. Compliance Code - Excavation
AS 2601 - Demolition of Structures
Building Act 1993 & Regulations 2018
AS 3660 - Termite Management
AS 3740 - Waterproofing
Domestic Building Contracts Act 1995
Electronic Appliances Code of Practice
Question 5
1 / 1 pts
Compliance with EPA requirements.
Building and construction sites create pollution, including different types of waste, noise and dust.
As a builder, you are responsible for the impact of your work on the health of people and the environment.
Which of the following are EPA issues? There are more than one.
Airborne dust
Noise
Sediment run-off control
Chemical spills
IncorrectQuestion 6
0 / 1 pts
What are the two main categories of regulated building contracts in Victoria?
Major Domestic Building Contract
Cost Plus Contract
Alterations and Additions Contract
Outdoor Building Projects Contract
Swimming Pool and Spa Contract
Victorian Kitchen Bathroom & Laundry Supply Install Contract
Question 7
1 / 1 pts
Obtain prices from a local building materials supplier, or refer to the Student Guide, to answer the following.
You require 12 lineal metres (LM) of LVL 140 x 45
What is the total cost?
Do not enter $, commas, or decimal point.
Enter your answer in the following format: ie 96
Question 8
1 / 1 pts
Registering for WorkCover Insurance
When must you register for WorkCover Insurance?
Select two (2) appropriate answers
You may log in to https://www.worksafe.vic.gov.au/insurance to obtain the relevant information
Generally, you must register for WorkCover insurance if you or your company employs any workers in Victoria.
If your company employs you personally, then you are a worker of your own company, and need to register
When you start a business
If you’re a sole trader
Question 9
1 / 1 pts
Employee or Contractor?
Select the answer that best matches the description.
The worker can't subcontract/delegate the work, ie. they can't pay someone else to do the work
Worker/Employee
Contractor
No answer text provided.
No answer text provided.
Question 10
1 / 1 pts
Employee or Contractor?
Select the answer that best matches the description.
The worker takes commercial risks, with the worker being legally responsible for their work and liable for the cost of rectifying any defect in their work
Contractor
Worker/Employee
No answer text provided.
No answer text provided.
Question 11
1 / 1 pts
Employee or Contractor?
Select the answer that best matches the description.
The worker is not operating independently of your business. They work within and are considered part of your business.
Worker/Employee
Contractor
No answer text provided.
No answer text provided.
Question 12
Not yet graded / 1 pts
List two estimating software systems commonly used in the building and construction industry.
Your answer:
DateBuild
Buildertrend
Question 13
1 / 1 pts
Using the Provisional sum in the contract for Cooke Street ($13,194.00) and the information below, answer the following questions.
Scenario: You have carried out the slab works but due to an excess of soil excavated, soil contamination, increased tipping costs and deeper beam depth require the actual cost has increased to $15,300.00 inc GST.
What is the Difference in cost between the Actual Cost of the Concrete Slab and the Provisional Sum Allowance?
This is the difference to be paid by or due to, the Owner.
Do not use the $ sign, however, you must enter the amount, including cents, as this is a claim for payment from your Client.
For example: 2,345.00
Scenario - Variations (V)
The Client requests a Variation to the Contract Works.
They wish to install joinery (cabinets and benchtop) in the Laundry, along the wall between the Laundry and Kitchen.
The Drawings show a 45 litre trough cabinet on the plan, however, this is an excluded item in the Contract, and is being supplied and installed by the Client.
The cost of the Variation is only for the joinery; there is no deduction required for the trough.
The price of the joinery with benchtops, supplied and installed is $745.00/LM excl. GST
Task: Based on the above information answer the following questions.
IncorrectQuestion 14
0 / 1 pts
Calculate the cost of the Variation for the Joinery EXCLUDING GST
Do not use $, comma (,) or decimal point (.)
Enter your answer as 1234
UnansweredQuestion 15
0 / 1 pts
Calculate the cost of the Variation for the Joinery INCLUDING GST
Do not use $, comma (,) or decimal point (.)
Enter your answer as 1234
UnansweredQuestion 16
0 / 1 pts
What is the GST amount in the Variation?
Do not use $, comma (,) or decimal point (.)
Enter your answer as 123
Question 17
Not yet graded / 1 pts
How should the variations be communicated and recorded on the plans to ensure that they are followed?
Your answer:
the builder cannot proceed with the work described in the variation until they receive signed consent from the client. The client is required to respond to the written notice of variation within five days, and claim for extension of time and money.
Question 18
Not yet graded / 1 pts
List two building project management software systems that could manage variations and client communications?
Your answer:
Procore
CoConstruct
Question 19
Not yet graded / 1 pts
You have been asked to supervise the work of another staff member. You have asked Kerry to estimate the brick work take off for the 68 Swinburne Rd job.
Task: Review the estimate Kerry created and identify any errors that were made when comparing with your calculations in Assessment Task 2.1. Write an email to Kerry explaining what was wrong and request that the estimate is rectified.
Kerry sent you the following email
Hi
I did the estimate for the bricks and found the following:
• Number of bricks overall is 3,800 x .73c
• Added 5% for wastage is $190
• Total cost estimate for this job is $2964
Let me know what you think.
Thanks
Kerry
Your answer:
Hi, Kerry
Thank you for your hard work
After I checked the data, I found the following errors:
• Number of bricks overall is 3,900 x .73c
• Added 5% for wastage is $200
• Total cost estimate for this job is $3000
Please check and modify again, and send it to me within 5 working days. thank you.
Kind regards,
Jianlan He
Question 20
1 / 1 pts
Kerry also wanted to include a clause in the contact that would allow for ‘rise and fall’ cost increase. Is this clause likely to be allowed in the contract?
Yes
No
|
|