刚才又参考了其他帖子同学的提示,貌似Interim OC确实是可以settle的但是NSW的规定是要拿到OC后14天才可以settle.我们这个节奏。。。汗。。24日拿到31日settle,还是Interim的。我担心的这么久都没有通过,是不是有什么不可弥补的质量问题?final OC如果一直没有拿到,会有什么问题吗?大家都什么想法吗?
CONVEYANCING (SALE OF LAND) REGULATION 2010 - SCHEDULE 2
2 Strata units bought off the plan
(1) The vendor must serve, at least 14 days before completion, an occupation certificate within the meaning of the Environmental Planning and Assessment Act 1979 (being an interim occupation certificate or a final occupation certificate) in relation to the building, or part of the building, of which the lot and access to the lot form part.
(2) For the purposes of this clause, the part of a building comprising access to a lot is any part of the building reasonably necessary for access to the lot.
(3) The purchaser does not have to complete earlier than 14 days after service of the certificate. |
|