第一次翻新浴室和厨房,请同学们帮忙看下这份报价,价格是否合理,坐标墨尔本
价格不包含拆除旧东西的工作,不包含淋浴房,洗台,浴缸等的安装,也不包含改管道的plumber工作
谢谢!!
Expected Duration: 14 working days Final Estimated Amount : $ 20,210.00
SCOPE OF WORK FOR BATHROOM
A. Kitchen ( 6000 * 4000) : $ 1,970.00
1. Put on drop-sheet all the way to the kitchen from the exit.
2. Install cement underlay for tiling.
3. Install tile on the floor.
4. Install grout on the tiles.
5. The client provide following items.
a. Ceramic tiles for floor : 30 m2
b. Grout : 10kg.
B. Shower room (1670 * 1780) : $ 3,060.00
1. Put on drop-sheet all the way from the shower room to the exit.
2. Cut the floor and make a shower base (900 * 900)
with sand and cement on the same site.
3. Install cement sheet on the shower walls.
4. Make shower niche (300 * 300) (option; $400)
5. Install ceramic tile underlay all the floor.
6. Do primer on the shower and the floor.
7. Do waterproofing on the shower walls.
8. Do waterproofing on the all the floor.
9. Install tiles on the floor.
10. Install tiles inside niche (If option taken)
11. Install tiles on the shower base.
12. Install tiles on the walls (2400 hight)
13. Remove the cornices.
14. Install the cornices.
15. Install silicon all the edges.
16. Patch cracks, holes and imperfections on the ceiling.
17. Sand and dust off prior for painting on the ceiling..
18. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
19. Apply two coat of water base on the ceiling.
20. The client provide following items.
a. Ceramic tiles
Floor : 5 m2 Walls : 17 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 1 kg. Walls : 4 kg.
c. Paint
Undercoat(water based) : 2L. Ceiling(flat) : 2L
C. Powder room ( 1670 * 1780) : $ 1,640.00
1. Put on drop-sheet all the way from the shower room to the exit.
2. Install ceramic tile underlay all the floor.
3. Install tiles on the floor.
4. Install tiles on the walls (2400 hight)
5. Remove the cornices.
6. Install the cornices.
7. Install silicon all the edges.
8. Patch cracks, holes and imperfections on the ceiling.
9. Sand and dust off prior for painting on the ceiling..
10. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
11. Apply two coat of water base on the ceiling.
12. The client provide following items.
a. Ceramic tiles
Floor : 5 m2 Walls : 18 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 1 kg. Walls : 4 kg.
c. Paint
Undercoat(water based) : 2L. Ceiling(flat) : 2L
D. Laundry ( 1930 * 3000) : $ 870.00
1. Put on drop-sheet all the way from the laundry to the exit.
2. Install ceramic tile underlay all the floor.
3. Install tiles on the floor.
4. Install tiles over the bench top 2 walls. (1530 hight)
5. Install silicon all the edges.
6. Repair a hole on the floor.
7. The client provide following items.a. Ceramic tiles
Floor : 5 m2 Walls : 18 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 1 kg. Walls : 4 kg.
E. Toilet 2nd floor (2440 * 970) : $2,030.00
1. Put on drop-sheet all the way from the toilet to the exit.
2. Install ceramic tile underlay all the floor.
3. Install villaboard on the side walls.
4. Install tiles on the floor.
5. Install tiles on the walls (2400 hight)
6. Remove the cornices.
7. Install the cornices.
8. Install silicon all the edges.
9. Patch cracks, holes and imperfections on the ceiling.
10. Sand and dust off prior for painting on the ceiling..
11. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
12. Apply two coat of water base on the ceiling.
13. The client provide following items.
a. Ceramic tiles
Floor : 3 m2 Walls : 20 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 1 kg. Walls : 5 kg.
c. Paint
Undercoat(water based) : 2L. Ceiling(flat) : 2L
F. Bathroom 2nd floor (2400 * 3200) : $ 4,640.00
1. Put on drop-sheet all the way from the bathroom to the exit.
2. Cut the floor and make a shower base (1400 * 900)
with sand and cement on the same site.
3. Remove the damaged board on the walls.
4. Install villaboards on the shower walls.
5. Repair holes on the floor.
6. Make shower niche (300 * 300) (option; $400)
7. Install ceramic tile underlay all the floor.
8. Do primer on the shower and the floor.
9. Do waterproofing on the shower walls.
10. Do waterproofing on the free standing bath walls.
11. Do waterproofing on the all the floor.
12. Install tiles on the floor.
13. Install tiles inside niche (If option taken)
14. Install tiles on the shower base.
15. Install tiles on the walls (2400 hight)
16. Remove the cornices.
17. Install the cornices.
18. Install silicon all the edges.
19. Patch cracks, holes and imperfections on the ceiling.
20. Sand and dust off prior for painting on the ceiling..
21. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
22. Apply two coat of water base on the ceiling.
23. Supply and install a frameless shower screen (2000 * 1100)
( option: $750)
24. The client provide following items.
a. Ceramic tiles
Floor : 10 m2 Walls : 29 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 3 kg. Walls : 8 kg.
c. Paint
Undercoat(water based) : 4L. Ceiling(flat) : 4L
G. Shower room 2nd floor ( 900 * 1440+ 3000 * 1800) : $ 4,440.00
1. Put on drop-sheet all the way from the bathroom to the exit.
2. Cut the floor and make a shower base (1440 * 900)
with sand and cement on the same site.
3. Remove the damaged board on the walls.
4. Install villaboards on the shower walls.
5. Repair holes on the floor.
6. Make shower niche (300 * 300) (option; $400)
7. Install ceramic tile underlay all the floor.
8. Do primer on the shower and the floor.
9. Do waterproofing on the shower walls.
10. Do waterproofing on the all the floor.
11. Install tiles on the floor.
12. Install tiles inside niche (If option taken)
13. Install tiles on the shower base.
14. Install tiles on the walls (2400 hight)
15. Remove the cornices.
16. Install the cornices.
17. Install silicon all the edges.
18. Patch cracks, holes and imperfections on the ceiling.
19. Sand and dust off prior for painting on the ceiling..
20. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
21. Apply two coat of water base on the ceiling.
22. Supply and install a sliding shower screen (2000 *1440)
( option: $1,200)
23. The client provide following items.
a. Ceramic tiles
Floor : 10 m2 Walls : 27 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 3 kg. Walls : 7 kg.
c. Paint
Undercoat(water based) : 3L. Ceiling(flat) : 4L
H. Toilet 2nd floor (1700 * 900) : $ 1,560.00
1. Put on drop-sheet all the way from the toilet to the exit.
2. Install ceramic tile underlay all the floor.
3. Install tiles on the floor.
4. Install tiles on the walls (2400 hight)
5. Remove the cornices.
6. Install the cornices.
7. Install silicon all the edges.
8. Patch cracks, holes and imperfections on the ceiling.
9. Sand and dust off prior for painting on the ceiling.
10. Apply one coat of sealer/undercoat prior to finish coat on the ceiling.
11 Apply two coat of water base on the ceiling.
12 The client provide following items.
a. Ceramic tiles
Floor : 2 m2 Walls : 13 m2
b. Grout (same or similar color of wall tiles and floor tiles)
Floor : 1 kg. Walls : 4 kg.
c. Paint
Undercoat(water based) : 2L. Ceiling(flat) : 2L
I. Payment Method:
* 10% on the sign the contract.
* 20 % on the start the job.
* 50% at the end of the week based on progress.
* 20% on completion of Job
J. Condition and Terms.
1. The quote amount is include all materials except provided by the clients.
2. The price is not include GST.
3. If mosaic tiles is used, extra cost ($ 50.00 sqm) will be charged.
4. If asbestos cement sheet is found, the removal will be organized by the
clients.
|
|