此文章由 jessica_cao 原创或转贴,不代表本站立场和观点,版权归 oursteps.com.au 和作者 jessica_cao 所有!转贴必须注明作者、出处和本声明,并保持内容完整
原帖由 H妈妈 于 2010-11-9 19:03 发表 
啊?怎么那么贵啊?贴出来明细让论坛上的专家们看看吧!我记得你的地只是有个下水道问题,但是地本身还算是平整工整的呀!太贵了!是不是他们放了很多allowance进去,in case遇到石头?其实真的应该找其他builder再看看的,有些只收5 ...
你大事干完了么?
我们的地后高前低,所以要求了step down edge beam,前面看上去就是要上几格楼梯才到前门的,感觉漂亮些.
明细如下:
1. Basic site cots for a standard site (M class slab)
$6900
2. Provide Earthworks including:
Vegetation scrape
Importing of fill
Exporting spoil from excavation including disposal fees
exporting spoil from piering
exporting spoil from drainage
$7400
3. Provide up to 60lm of bored concrete piers under the slab
$5520
4. Concrete pump
@1100
5.Additional Material Handling due to restricted access or excessive site fall, including small load deliveries, specialised scaffolding & double handling of materials
$2000
6. Dropped edge beams to be house as required by Local Authorities and site conditions including increase ceiling height to garage by 514mm and provide 2 internal steps
$14850
7.Retaining walls by owner
(这个还没算钱我们自己干的活)
8.Extend Underground power suppply over 9m run.
$702
9. Metal Service Pole at the boundary, connected to overhead supply on the same side of the road.
$1650
10. Provide additional run of 90mm stormwater line.
$504
11. Extend 100mm sewer line.
$1044
12. Near side (of road) water tapping and connection from mains to meter.
$820
13. Additional length of 20mm dia water service over 9m run.
$312
14. Provisional Allowance for footpath opening to connect to sewer and stormwater.
$5000
15. Provisional allowance for On Site Detention.
$22000
总共$69802
然后BASIX: $10990.
aaaa |
|