包括以下:
o Levels and Details Survey,
o Design Concept:
o Measuring the existing building,
o As built (existing) plans,
o Site analysis and evaluation of council requirements,
o Preparation of concept drawings,
o 1 x meetings to review the concept design drawings,
o Development Application:
o Preparation of developed plan, elevation and section drawings,
o Further development of drawings,
o Identification of exterior materials and finishes,
o 1 x meeting to signoff drawings for DA lodgement,
o Site and analysis plans,
o Architectural drawings,
o Floor space ratio,
o Shadow Diagrams,
o External Finishes,
o Completion of council application forms,
o Lodging required documents with council,
o Statement of Environmental Effects,
o Heritage Impact Statement,
o BASIX Certificate
o Project Management |
|