fingerwater 发表于 2018-7-29 12:18 
问题这个法律条款支持吗?我的律师不知道是敷衍我还是什么,说这个除了结构变化,否则没有办法不settle。 ...
我的 contract 上写明 fix 完 known defects 才 pay final payment。
如果我和 builder 都 sign 了contract ,任何一方不 follow 就是 breach the contract, 可以经法律追究损失的。
如果你在 Melbourne, 你可以电 Victoria consumer affairs
https://www.consumer.vic.gov.au/ ... g-for-building-work
Making final payment
The building project is complete, and you make the final payment, when the work is finished in accordance with plans and specifications and the Occupancy Permit has been issued (for a new home) or a Certificate of Final Inspection has been issued (for an extension or renovation). The builder is not entitled to the final payment until then.
You can pay an independent building consultant to check for defects or unfinished work, and to advise you of any issues which have affected completion of the project. If you have concerns:
make a list of any work that you believe is faulty or incomplete
speak with your builder immediately about your concerns
put your request and any agreements made with the builder to finish work in writing, and send it by registered post.
If you are in dispute about areas of work, contact our Building Information Line on 1300 55 75 59 between 9:00 am to 5:00 pm, Monday to Friday (except public holidays). Calling this number costs the same as a local call. Additional charges may apply if you are calling from overseas, on a mobile or payphone. |
|