我有一份靠谱的solar farm可行性报告,link发不了我直接贴结论:
The review of the electricity network in the District identified limited opportunities to connect a
10 MW solar farm at competitive cost. At the 1 MW scale, the opportunity for cost effective connection is greater, however the economics are less favourable. Investigation of an intermediate size solar farm of around 5 MW could be undertaken to understand the cost – value gap at this scale and the impacts of the grid network.
The solar resource information used is based on a 5 km grid that introduces some artefacts into the preferred area maps. It is recommended that higher resolution solar data is obtained and used in the mapping to avoid artefacts.
It is noted that this analysis did not consider all possible variables influencing development decision. The cost of land access not considered as a variable across the District, although it is generally known that the areas of higher and more reliable rainfall are more valuable. Further investigations could incorporate rainfall information as a proxy for land value.
30 ITP/A0121 – November 2013
Solar Farm Feasibility Study |
|