俺去年拿的证, 培训机构找的Yellowhouse, 三天课程拿Foundation, 再多上两天拿Practitioner, 前面那个好过,后面那个不好过。想做PM, Practitioner是必须的。
题库没有,他们倒是给了不少资料和总结图,还有两套Sample Paper, 一套75道题,随便写几个:
Which is one of the six aspects of project performance that needs to be managed?
a. Customers
b. People
c. Benefits
d. processes
Identify the missing words in the following sentence
During the Controlling a Stage process, the [ ? ] is checked for any new or revised threats and their possible impact on the Business Case.
a. Benefits Review Plan
b. End Stage Report
c. Risk Register
d. Risk Management Strategy
What PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
a. Continued business justification
b. Manage by exception
c. Focus on products
d. Manage by stages
|